1. 01

    Do I need a geotechnical investigation before applying for a building permit?

    In most cases, yes. The BC Building Code requires that the bearing capacity and classification of the site be established before a foundation can be designed. Most municipalities in BC — including Vancouver, Burnaby, Surrey, and Coquitlam — require a sealed Geotechnical Investigation Report (GIR) as part of the development permit or building permit application package for any new structure with a foundation.

    The requirement also applies to significant additions, below-grade parkades, and projects on sites with known soil or groundwater risks — steep slopes, proximity to watercourses, suspected fill, or soft compressible soils.

    The GIR must be prepared and sealed by a Professional Engineer registered with Engineers and Geoscientists BC (EGBC). Commission the investigation as early in the design process as possible: foundation recommendations from the GIR feed directly into the structural engineer's design, and a late investigation can hold up the entire permit process.

  2. 02

    How long does a geotechnical investigation take?

    A typical geotechnical investigation for a mid-size development project in BC takes 6 to 10 weeks from authorization to sealed report. The breakdown is roughly as follows:

    Program design & drilling permits — 1 to 2 weeks. We prepare the field program and coordinate access, drilling subcontractor scheduling, and any utility locates or right-of-way permits required.

    Field work — 1 to 3 days on site for most residential and commercial projects, depending on the number of boreholes and site access conditions. Larger or more complex programs take longer.

    Laboratory testing — the most variable phase. Standard index tests (moisture content, Atterberg limits, grain size) take 2 to 3 weeks. Consolidation testing, required when settlement of fine-grained soils is a concern, can run 4 to 6 weeks.

    Report preparation & sealing — 2 to 3 weeks once lab results are in hand.

    Expedited programs are possible for straightforward sites. Preliminary findings can be communicated verbally or in draft form before the formal sealed report is issued if the project schedule requires it.

  3. 03

    What information should I have ready before contacting a geotechnical engineer?

    The more context you provide upfront, the more precise the scope and fee estimate we can give you. At a minimum, have the following ready:

    Site information — address or legal description, any known site history (prior industrial use, fill placement, previous structures, slope movement, flooding).

    Project type and scale — residential, commercial, or infrastructure; number of storeys; whether below-grade levels or deep foundations are planned.

    Timeline — when you need the report for permit submission or design coordination.

    Other consultants — if a structural or civil engineer is already engaged, their preliminary foundation concept and column loading estimates allow us to scope the investigation much more accurately.

    Existing soil reports or borehole logs from adjacent or nearby sites are also useful if available — they can reduce the scope of the new investigation or flag specific risks to investigate.

  4. 04

    What is the difference between a Geotechnical Investigation Report (GIR) and a Phase I Environmental Site Assessment (ESA)?

    They answer fundamentally different questions and should not be confused, although both are commonly required for the same development project.

    A GIR characterizes the engineering properties of the subsurface — soil strength, groundwater depth, compressibility, seismic site class — and provides foundation recommendations for structural design. It is a building engineering deliverable that feeds the building permit process. No contamination assessment is performed.

    A Phase I ESA is an environmental review of potential contamination. It examines historical land use records, aerial photographs, regulatory databases, and site conditions to determine whether activities that could have caused soil or groundwater contamination occurred on or adjacent to the site. Critically, no soil samples are collected in a Phase I — it is a records and reconnaissance exercise.

    If the Phase I identifies concerns, a Phase II ESA follows, which involves actual soil and groundwater sampling to confirm or rule out contamination. Phase II findings may then trigger a remediation scope.

    In short: the GIR asks whether the ground can safely support a structure. The ESA asks whether the ground has been compromised by its history. Both are signed by a qualified professional, but they serve different regulators and different stages of the approval process.

  5. 05

    When is a shoring design required in BC?

    WorkSafeBC regulations require worker protection for any excavation deeper than 1.2 metres. In urban construction, this almost always means a formal shoring system — there is rarely enough room for the setback that an unsupported slope requires when adjacent property lines, existing buildings, and buried utilities are present.

    A sealed shoring design prepared by a P.Eng. is required by WorkSafeBC whenever a shoring system is used, and the design documents must be available on site throughout construction. Municipalities typically also require the shoring design — along with a monitoring program — as a condition of the building permit for any deep excavation.

    Practically, any project involving an underground parkade, a foundation deeper than about 1.5 metres in an urban setting, or excavation within the zone of influence of an adjacent structure will require a formal shoring design.

    The shoring design draws directly on geotechnical investigation data — soil strength parameters, groundwater levels, and surcharge loading from adjacent structures. Running both scopes through the same firm avoids translation errors and compresses the overall schedule.

  6. 06

    What does a geotechnical engineer do during construction monitoring and why is it required?

    Construction monitoring is the phase where the geotechnical engineer verifies that actual site conditions match the assumptions made during investigation and design — and responds when they don't.

    At foundation level, we observe and document the exposed subgrade, confirm that the bearing stratum is present at the design elevation, and identify anomalies — soft spots, undocumented fill, unexpected groundwater — that require a design response before concrete is placed. For shoring projects, we review the installation of sheet piles, soldier piles, and tieback anchors, and we interpret inclinometer and settlement monitoring data throughout the excavation sequence to catch developing movement early.

    In BC, the Building Code requires the engineer of record to provide a Letter of Assurance (Schedule C-B) confirming that construction was carried out in substantial conformance with the design. For the geotechnical engineer, that letter cannot be issued without documented field observations during construction. It is a regulatory requirement, not optional.

    Beyond compliance, monitoring protects everyone on the project. Discrepancies between design assumptions and actual conditions are caught while there is still time to respond — not after the slab is poured or the adjacent building has cracked.